Next Steps

The redevelopment of Cumbernauld town centre is a major regeneration project, the largest of its kind in North Lanarkshire, which means it is a long-term development that will deliver positive transformative change for the Cumbernauld community.  

Although our plans involve the complete replacement of the centre with a new town centre including the proposed development of a Town Hub with education, health, community and leisure facilities, public transport improvements and a modern bespoke retail and commercial offer, we can’t simply knock down the centre tomorrow.  

Lots of businesses still currently trade from the centre, many of whom have lease agreements extending well into the future. We must also plan the regeneration of the centre in a sensitive manner, helping, where possible, to sustain and retain these businesses within Cumbernauld.  

The regeneration of Cumbernauld town centre is a long-term project and it is anticipated that it will take 8 to 10 years to complete the demolition of The Centre Cumbernauld. During that time the centre will continue to be operational, although some businesses may be offered the opportunity to re-locate within the centre to support the two-stage demolition strategy. 

The table below sets out some of the key milestones we expect to achieve over the next decade in relation to this project. This page will be updated regularly in line with developments.

Milestones Estimated timescales
North Lanarkshire Council purchases The Centre Cumbernauld June 2023
Engagement with businesses regarding future options and development of a two-stage demolition strategy 2024
Progress development of proposals for the phased redevelopment of the town centre, including traffic/transportation assessments 2024 - 2025
Initial public engagement commences with various stakeholders 2024 - 2026
Public consultation commences on draft proposals 2025 - 2026
Stage 1 demolition of The Centre Cumbernauld begins. This will be to the most recently developed part of the shopping centre at Teviot Walk / Teviot Square. Temporary greenspace will then be put in place until the centre is fully demolished.  2027 - 2028 (Estimated start date)
Stage 2 demolition of The Centre Cumbernauld commences to the older part of the shopping centre (on both sides of Central Way, around Tweed Walk and Tay Walk). 2031 - 2033 (Estimated start date)

Funded by UK Government

Levelling Up Logo (Blue on White)

Page last updated:
18 Apr 2024

Help us improve this pageClose

We're sorry this page didn't meet your expectations this time. Please let us know if you have any feedback to help us improve the content.

If you have a question or comment about a council service or would like a reply, please contact us.

Thank you for your feedback