Tower re-provisioning

We are committed to identifying and improving future housing options for people living in high-rise homes in North Lanarkshire.

In 2017, we announced a major change in our housing policy in consultation with the residents of North Lanarkshire, with plans agreed to demolish a number of towers and low-rise blocks and replace them with modern homes fit for the future. This forms part of our Plan for North Lanarkshire, which includes providing 5000 new affordable homes for rent by 2035.

Phase 1 update

Phase 1 of our reprovisioning programme is on track with 94% of the properties identified now vacant. Our ambition to replace all tower blocks and some low-rise flats with high quality, modern, energy efficient homes is becoming a reality with building and regeneration works now ongoing across our communities.

Phase 1 Progress
TowerVacant propertiesStatus
Northburn Low-Rise Airdrie27 (100%)Complete
Holehills, Airdrie138 (100%)Complete
Burnside Court, Coatbridge44 (100%)Complete
Gowkthrapple Low-Rise, Wishaw304 (100%)Complete
Shawhead Low-Rise, Coatbridge176 (100%)Complete
Coursington, Allen, Drafffen High-Rise, Motherwell351 (100%)On Site
Jackson High-Rise, Coatbridge192 (100%)On Site
Allershaw High-Rise Wishaw70 (100%)On Site
Dunbeth High-rise, Coatbridge186 (100%)On Site
Highcoats, Coatbridge180 (94%) figure includes those allocated to Displaced Citizens and Temp AccommodationRe-programmed
Birkshaw High-Rise, Wishaw69 (99%)  figure includes those allocated to Displaced Citizens and Temp AccommodationRe-programmed
Total1737 (100%) 

Phase 2 regeneration proposals

As phase 1 of our regeneration plans have progressed, we are now moving on to phase 2.

Phase 2 regeneration plans identified several prominent multi-storey blocks in Motherwell, a tower in Coatbridge and low-rise blocks in Airdrie, Coatbridge, Kilsyth, Motherwell & Wishaw for potential demolition.  Following a consultation exercise carried out in May 2023, where over 80% of residents within the second phase of the re-provisioning programme advised they were in favour of our proposals, a report was submitted to the Housing committee in August 2023 where the proposals for the next phase were approved.

Properties included in Phase 2 demolition programme

All residents of the blocks included within the phase 2 will be contacted as the programme progresses by staff from the local housing offices.

If you require any further information please contact your local housing office.

High-rise
AddressArea Vacant PropertiesStatus
Anderson TowerMotherwell35 (52%)Being Vacated
Oakfield TowerMotherwell20 (30%)Being Vacated
Albion TowerMotherwell18 (27%)Being Vacated
Airbles TowerMotherwell21 (32%)Being Vacated
Whamond TowerMotherwell23 (35%)Being Vacated
Glen TowerMotherwell43 (41%)Being Vacated
Woodside TowerMotherwell49 (47%)Being Vacated
Witchwood CourtCoatbridge46 (55%)Being Vacated
Low-rise
AddressArea Vacant PropertiesStatus
McClurg Court 1 - 56Motherwell30 (54%)Being Vacated
Rennie Road (12 blocks) Kilsyth 49 (83%)Being Vacated
Kennedy Drive (4 blocks)Airdrie 17 (42%)Being Vacated
Glencraig Street 1 - 19Airdrie4 (40%)Being Vacated
Kippen Street (7 blocks)Airdrie29 (41%)Being Vacated
Greenfield Drive (4 blocks)Wishaw31 (70%)Being Vacated
Glasgow Road (3 blocks)Wishaw33 (78%)Being Vacated
Main Street (236-284a)Wishaw  
Maxton CrescentWishaw40 (100%)Vacant

 

All tenants whose homes are in the second phase for demolition will be contacted by their local area housing office and housing options interviews will be carried out. Housing Advisors will discuss tenants’ housing needs to identify suitable housing options based on their circumstances and in line with the general allocations policy.

What happens next?

Regular updates will be provided through local press, social media and our website.

Page last updated:
26 May 2026

Help us improve this pageClose

We're sorry this page didn't meet your expectations this time. Please let us know if you have any feedback to help us improve the content.

If you have a question or comment about a council service or would like a reply, please contact us.

Thank you for your feedback