St Stephen's Community Hub

St Stephen's Community Hub
Project timeline
Item                                       Planned
Start on site March 2025
Construction completion Phase 1Q4 2026
Construction completion/handoverQ2 2027

Newsletters from Morrison Construction

Please note - the first and current newsletters are listed below. If you wish to see the other newsletters please email hubdeliveryteam@northlan.gov.uk

A new community hub that includes:

  • St Stephen's Primary School
  • Language and Communication Support Centre
  • Nursery Class
  • Community Facilities
  • Partnership Zone

This development provides a modern facility that supports the needs and aspirations of St Stephen's Primary School pupils present and future, along with the wider local community.

 

Latest news/progress

Morrison Construction appointed by Hub South West as the preferred contractor for the project

The wider design team consists of:

  • Ryder Architecture (Architect)
  • Struer (Structural and Civil Engineers)
  • RSP Consultant Engineers (Mechanical and Electrical Engineers)

 

Pupils' First Day

Children arrived on Wednesday 11 November to find a modern new home, built to support learning for pupils today and in the future. The hub will also serve the wider local community, by providing accommodation for a range of community groups.

Page last updated:
19 Nov 2026

Help us improve this pageClose

We're sorry this page didn't meet your expectations this time. Please let us know if you have any feedback to help us improve the content.

If you have a question or comment about a council service or would like a reply, please contact us.

Thank you for your feedback