Work is continuing on plans to regenerate Millcroft Road in Cumbernauld through the acquisition and demolition of poor quality flatted properties.
The Compulsory Purchase Order for the 169 flats across blocks C, D and E was confirmed by Scottish Government Ministers in January 2025.
Since then, the council has made significant progress, with 128 property acquisition offers now accepted by owners. The number of occupied properties has also fallen from 99 in August 2025 to 40 in November 2026.
A dedicated project team is working with residents, landlords and local housing providers to support the rehousing process. The council has also appointed a temporary liaison officer to increase direct contact with residents.
The Vesting Date, when the council will take legal ownership of any remaining properties through the compulsory purchase process, has now been set for 31 March 2027.
Housing Convener Councillor Michael McPake said: “This is an important regeneration project for Carbrain, and we are making steady progress towards delivering the new, high quality housing the community need.
“We recognise the impact this process has on people currently living at Millcroft Road, and our priority is to work closely with them to provide support and help them move to suitable homes.
“Once the properties have been acquired and all properties vacated, we can move towards demolition and the next stage of the project, which will deliver 72 modern, energy-efficient homes for social rent.”
Demolition is currently programmed to begin in 2028, with the new homes expected to be completed in 2032.