Skip to main content

East Airdrie Link Road - What's happening next?

This is a large project that will take some years to complete. 

Once the preferred option is confirmed we will move forward to Stage 3 of the project.

Stage 3 will develop the design for the route option chosen. It will include:

  • the preliminary design of the road
  • funding approvals
  • getting planning permission

We will continue to work with NHS Lanarkshire on the position for the new road within the Monklands Replacement Hospital preferred site at Wester Moffat.

We will consult with stakeholders through the Stage 3 design process.

All of this work and more will be required before we will be able to start building the road.

Our expected timetable

  • started site investigation works - 2022
  • start Stage 3 preliminary design - early 2024
  • outline business case for City Deal funding - May 2024
  • planning application - early 2025
  • construction - 2028 to 2030 (two-year construction approximately)

Page last updated:
01 Feb 2024

Help us improve this pageClose

We're sorry this page didn't meet your expectations this time. Please let us know if you have any feedback to help us improve the content.

If you have a question or comment about a council service or would like a reply, please contact us.

Thank you for your feedback