Homes we're building and future sites
Future development sites
We have appointed a design team to deliver the next phase of new build houses. The design team are responsible for producing a site layout and applying for statutory consents such as planning and Scottish Water approvals.
We are also in the process of appointing contractors to carry out the construction works. The next phase of sites to be developed and the estimated start dates for developing these sites are detailed below.
Site name | Estimated number of homes | Estimated site start |
---|---|---|
Laburnum Road, Viewpark | 26 | October 2025 |
Caledonian Road, Wishaw | 15 | October 2025 |
Graham Street, Wishaw | 13 | October 2025 |
King Street, Wishaw | 5 | October 2025 |
Stewarton Street & Kings House, Wishaw | 18 | October 2025 |
Main Street, Glenboig (former Police station) | 7 | March 2026 |
Kildonan Street, Coatbridge | 43 | March 2026 |
Bank Street, Coatbridge | 16 | March 2026 |
Dalzell Drive, Motherwell | 24 | 2026 |
Hill Street, Caldercruix (Former St. Mary's PS) | 25 | 2026 |
Newton Drive, Newmains (Former St Brigid's PS) | 35 | 2026 |
Tay Street, Coatbridge (Former Pentland PS) | 16 | 2026 |
Gartlea Road, Airdrie (Coats House) | 28 | 2026 |
Elm Crescent, Viewpark (Former Muirpark care home) | 25 | 2027 |
Cumbernauld Village School, Cumbernauld | 8 | 2027 |
Coats Street, Coatbridge (re-provisioning) | 56 | 2027 |
Coursington, Motherwell (re-provisioning) | 84 | 2027 |
Dunbeth, Coatbridge (re-provisioning) | 114 | 2027 |
Kildonan Street, Coatbridge (Former Portland HS) | 16 | 2027 |
Hattonrigg Road, Bellshill | 20 | 2028 |
Main Street, Wishaw (Anvil block) | 32 | 2028 |
Burngreen, Kilsyth | 10 | 2028 |