Orbiston Community Hub will provide a 21st-century facility for the Orbiston community which will include:
- Sacred Heart Primary School
- Lawmuir Primary School
- Family Learning Centre (0-5 years)
- Community Centre (which will replace Joe McKay Centre)
- Partnership Zone
We're committed to delivering an inclusive learning environment where state-of-the-art facilities are provided for its children, young people and members of the community.
A further focus on health and wellbeing will ensure this commitment extends to outdoor facilities and these will provide enhanced leisure and recreational facilities for all members of the community.
Proposals
The amenities will extend to high quality outdoor and indoor sports facilities, extensive landscaped shared playground for both schools and a dedicated outside play space for the Family Learning Centre, enthusing the youngest of learners.
The design of the Orbiston Community Hub is currently on track to deliver the council's first fully electric Town & Community Hub development which represents a significant and fundamental step for the council in their path towards Net-Zero.
This Hub will deliver on average a 90% reduction in carbon emissions and 60% reduction in energy consumption, compared to the estimated performance of the existing Lawmuir and Sacred Heart Primary schools.
Location of Orbiston Community Hub
Latest news/progress
Morgan Sindall has been appointed by Hub South West as the preferred contractor for the project.
The wider design team consists of:
- Keppie Design
- Curtins (Civil and Structural Engineers)
- RSP (Mechanical and Electrical Engineers)
- Hirst Landscape Architects
The Intelligent Briefing works are now complete and the team are progressing with the pre-construction design and activities. The next public consultation events are being scheduled for May 2022.
For more information visit the Orbiston Community Hub website.
Newsletters from Keppie Design
Please note that the first and current newsletters are online. If you wish to see other newsletters, submit your request using the contact us mailbox.
Newsletter 004 - May 2022
Newsletter 001 - May 2021
Item | Planned |
---|---|
Start on site | Q1 2023 |
Construction completion/Handover | Q3 2024 (phase 1) |