Skip to main content
Close notification
Scheduled maintenance

We’re carrying out essential maintenance to our website from noon Friday 26 April, until noon Monday 29 April. Some of our online services may be unavailable during this time.

Improving access through Ravenscraig

Next steps and timeline

The project will be delivered as part of the Glasgow City Region City Deal.

This is a large and complex project that will take several years to complete and will be delivered in different phases. This will ensure the new infrastructure is delivered when it's needed, while also ensuring investment in the development of the masterplan is maintained and the our financial commitment is managed alongside its many priorities. 

The first thing we have done is create a new railway bridge that the road will go under and connect with Ravenscraig.

The dates we expect the different works to start

Ravenscraig Access Infrastructure South

  • Completing the bridge crossing under the West Coast Main Line Railway - completed September 2023. 
  • Building the dual carriageway from Ravenscraig Regional Sports Facility to Motherwell and the junction at Airbles Road/Windmillhill Street: 
  1. site clearance and building demolition works begin spring 2024 
  2. advance groundworks to begin during 2024  
  3. main works begin during 2025 and completed during 2026 
  • Completing the dualling of Airbles Road - begins early 2028 

Ravenscraig Access Infrastructure North

  • Upgrading 3km of the A723 from the New Craig Road junction at Ravenscraig to the M8 at Holytown - the construction programme to be updated during 2024.

Page last updated:
22 Feb 2024

Help us improve this pageClose

We're sorry this page didn't meet your expectations this time. Please let us know if you have any feedback to help us improve the content.

If you have a question or comment about a council service or would like a reply, please contact us.

Thank you for your feedback